R03-076RESOLUTION NO. R03- O'1 ~O
A RESOLUTION OF THE CITY COMMISSION OF THE
CITY OF BOYNTON BEACH, FLORIDA, AUTHORIZING
EXECUTION OF AMENDMENT NO 1 TO TASK ORDER
NO. 14 TO CH2M HILL, INC., IN THE AMOUNT OF
$246,579.00 FOR THE PROFESSIONAL DESIGN,
PERMITTING, BIDDING, CONSTRUCTION PHASE AND
RESIDENT OBSERVATION SERVICES FOR NE 17TM
AVENUE DRAINAGE IMPROVEMENTS AND WATER
MAIN REPLACEMENT PROJECT; AND PROVIDING AN
EFFECTIVE DATE.
WHEREAS, on June 18, 2002, the City Commission approved Task Order 14,
authorizing CH2M Hill Inc., to complete the design for Phase 1 of this project, that consisted
of surveying and geotechnical data collection, runoff modeling, preparation of a preliminary
design, and to conduct a preliminary meeting with the SFWMD to present the project and
discuss permitting requirements; and
WHEREAS, in addition, CH2M Hill prepared a Preliminary Design Memorandum
outlining the design elements and the technical specifications/standards that form the basis of
the detailed design as well as an estimate of probable construction cost; and
WHEREAS, Task Order No. 14 is now 100% complete in accordance with the
approved schedule and within the funding limit; and
WHEREAS, professional services covered in this amendment to Task Order No. 14
include complete design, permitting, bidding, and construction phase services throughout a
projected 270 day construction period, Final Acceptance and project closeout.
WHEREAS, the City Commission, upon staff's recommendation, has deemed it
appropriate, and in the best interests of the public, to approve this amendment to Task Order
No. 14 for CH2M Hill., for the professional design, permitting, bidding, construction phase
and resident observation services for NE 17th Avenue Drainage Improvements and Water
Main Replacement Project.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COMMISSION OF
THE CITY OF BOYNTON BEACH, FLORIDA, THAT:
S:\CA\RESO~Agreernents\Task - Change Orders\CH2M Hill Task order - Amd to 14.doc
Section 1. The foregoing "Whereas" clauses are hereby ratified and confirmed as
being true and correct and are hereby made a specific part of this Resolution upon adoption
hereof.
Section 2. The City Commission of the City of Boynton Beach, Florida does
ihereby authorize and direct the approval and execution of Amendment No. 1 to Task Order
14 for CH2M Hill, in the amount of $246,579.00 for professional design, permitting, bidding,
iconstruction phase and resident observation services for NE 17th Avenue Drainage
Improvements and Water Main Replacement Project.
Section 3. This Resolution shall become effective immediately upon passage.
PASSED AND ADOPTED this ~ day of May, 2003.
ATTEST:
S:\CA\RESO~greements\Task - Change Orders\CH2M Hill Task order - Amd to 14.doc
Task Order No. 14- Amendment No. 1
Completion of Water and Stormwater Design
and Services During Construction
A. Background
CH2M HILL (CONSULTANT) has submitted the Preliminary Design of the N.E. 17th
Avenue Drainage Improvements and Water Main Replacement for the CITY of Boynton
Beach (CITY). Based on approval of the Preliminary Design, the CITY requested that
CONSULTANT provide design, permitting and services during construction (SDC)
assistance to the CITY in the execution of this project. The project is to be executed using the
traditional design, bid, and construct method.
This Amendment No. 1 to Task Order 14 addresses fees for professional services to provide
design, permitting, bid phase, SDC and resident observation services.
B. Scope of Services for Phase I
Task 1 - Design
The CONSULTANT will provide professional engineering services to the CITY for the
replacement of the existing asbestos cement water mains and installation of new storm
water improvements within the project area. The work will include preparation of Drawings
and Specifications to be used for bidding and construction.
The specific scope of services to be provided by CONSULTANT in this Amendment No. 1
includes the following:
1. Call utility location company, such as "No-Cuts", and perform site investigation
activities including a "field survey" of the project area to verify water line, sanitary
sewer, and other utilities locations and aligrtments are consistent with that shown on
utility record drawing information. Verification is to be by visual observation of surface
features of utilities (i.e., manholes, valve boxes, cable boxes, fiberoptic markers, etc.).
Review available utility plans, atlases, and maps of the area for location of existing
utilities. Coordinate the proposed water main and storm water piping alignments with
existing utility alignments to avoid conflictive routings to the extent possible.
Swale improvements and sidewalk replacement will be depicted by use of typical
standard sections and details keyed to the plan drawings. Driveway aprons will remain
as is and will not be replaced unless impacted by construction activities. Swales will be
improved on both sides of the road to promote enhanced area drainage.
Topographic details such as fences, sidewalks, walls, curbs, vegetation, signs poles, etc.
will be noted to the extent that they may be materially affected by the construction of the
swale, water main, storm water improvements, and sidewalk improvements.
o
DFB\DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 1
TASK ORDER NO, 14 - AMENDMENT NO, 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
Existing underground utilities will be shown on the Drawings based on best available
information obtained from Utilities and as verified by the field survey information
discussed above. Utilities shown are only those located within the work area that will
materially affect construction of the improvements (i.e. water or sewer mains, telephone
conduits and cable, fiber optic or electrical lines). CITY utility locations will be verified
by CITY personnel and a utility locating service, such as "No Cuts".
Drawings will be provided to the CITY at the 60, 90, and 100 percent stages of design
completion. The 60 percent drawings will provided in half-size format and the 90 and
100 will provided in full-sized format. Drawings for permit review will be full size
format.
o
The Drawings will show locations of new and existing water lines, existing sanitary
sewers, and storm water inlets (if any). Streets, driveways, and sidewalks, will be
outlined on the Drawings. Plan drawings will be at a scale not smaller than 1-inch
equals 20 feet and will be double panel format.
Upon completion of the 60% drawings, CONSULTANT will supply the CITY four (4)
sets of review documents. The CONSULTANT will attend a 60% workshop with CITY
personnel to receive and discuss review comments regarding the documents. The CITY
will provide CONSULTANT with a marked set of the documents containing the CITY's
consolidated comments for use in preparation of the next stage design deliverable. For
the 60% deliverable, a table of contents listing of specifications will be provided.
Upon completion of the 90% drawings, CONSULTANT will supply the CITY two (2)
sets of review documents. The CONSULTANT will attend a 90% workshop with CITY
personnel to receive and discuss review comments regarding the documents. The CITY
will provide CONSULTANT with a marked set of the documents containing the CITY's
consolidated comments for use in preparation of the next stage design deliverable. For
the 90% deliverable, draft specifications will be provided.
10. Upon completion of the permit drawings, CONSULTANT will supply the CITY three
sets of the final documents with appropriate copies of permit applications for signature.
The CONSULTANT will transmit permits to appropriate agencies on behalf of the CITY.
11. The storm water improvements and new water main will be located within the right-of-
way of neighborhood streets.
12. The location and elevation of CITY established horizontal and vertical control (if any)
will be listed on appropriate plan sheets.
13. CONSULTANT will attend two Community Involvement Meetings (CIM).
14. CITY standard developed details applicable to the work will be incorporated into the
Drawings. CONSULTANT will modify, as necessary, the CITY standard details.
15. Specifications and Contract Documents for bidding purposes are to be prepared by the
CONSULTANT for the water main and storm water improvements. These documents
are to reflect the following:
DFB~DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 2
TASK ORDER NO. 14 - AMENDMENT NO. I COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
· Contract Documents will use the CITY's existing "Front-End" conditions modified
by the CITY as appropriate for this project. Division 1 through 16 technical
specifications will utilize the CITY's master specifications modified by
CONSULTANT as appropriate for the project. All proposed modification to CITY's
specifications will be submitted to CITY for approval of modifications.
· Separate bid schedules will be provided for the water main and stormwater
improvements.
· The new water main will consist of 8-inch cement lined ductile iron pipe and fittings.
· The existing water mains will be abandoned in place or removed and disposed of.
Removal and disposal of asbestos cement lined piping to be consistent with worker
safety regulations, as specified in the documents.
· Installation of meter service connections will be included in the Contractor's scope of
work on a unit price basis. Approximate locations of service connections will be
identified on the drawings to assist the Contractor in establishing an appropriate
unit price for bidding.
16. An opinion of probable construction cost based on the 90 and 100 percent drawings and
specifications will be prepared. The cost estimate format will be consistent with the bid
proposal for the project. The cost opinion will be provided to the CITY at the time the
advertisement for bids is published.
17. The project drawings are expected to consist of the following sheets:
Estimated Sheet Count for
N.E. 17th Avenue Water Main and Stormwater Improvements
City of Boynton Beach
Sheet No. Drawing No. Description
1 G-0 Cover Sheet (Title & Vicinity Map)
2 G-1 General Notes, Legend, Abbreviations
3 G-2 Index Sheet
4-11 C-1 to C-8 Water Main and Swale Improvements -- Plan at 1" = 20'
(Double Panel Format)
12 D-1 Civil Standard Details (Restoration)
13 D-2 Water - Standard Details, Thrust Restraint Schedule
14 D-3 Water - Standard Details
15 D-4 Drainage - Standard Details
16 D-5 Drainage - Standard Details
Task 2 - Permitting
The CONSULTANT will assist the CITY in obtaining Palm Beach County Public Health
Department (PBCPHD) permits for the water main replacement by completing the permit
forms for CITY approval/signature and providing required drawings and specifications
necessary to obtain the permits. Permit application forms, including drawings and
DFB\DRAFT TASK ORDER 14AMEND 1 04 02 03.DOC 3
TASK ORDER NO. 14 - AMENDMENT NO, 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
specifications, for permitting through the PBCPHD will be submitted to the CITY
concurrent with delivery of the 90% design documents. The FDEP "Long-Form" permit
application is required as the project is in excess of 5,000 lineal feet and the new water mains
are to be relocated (i.e., not in the same trench as the existing lines). Fees will be paid by the
CITY. The CONSULTANT will also assist the CITY in obtaining South Florida Water
Management District (SFWMD) permits for the construction of exfiltration trenches by
completing the permit forms for CITY approval/signature and providing required
drawings and background information. Permitting for the SFWMD will be performed
concurrently with issuance of the 90% design documents. According to a pre-application
meeting held with SFWMD, the completion of the "Standard General" Sections A, C, and E,
of the Environmental Resource Permit application will be reqttired for this project. This
assumption will be used to budget the labor effort for this task. Permit fees will be paid by
the CITY.
Two copies of the final permitting packages (plus the number of agency required copies)
will be submitted with the 90% plans for submittal to the PBCPHD and SFWMD by the
CITY.
CONSULTANT will prepare two (2) response to each "request for additional information"
made by each regulatory agency following submittal of the permit applications. Additional
responses to agency requests for additional information will be considered an Additional
Services item.
Preparation of other permits for the above agencies (or for other regulatory agencies)
beyond that specified above will be considered an Additional Services item. Examples of
typical permits not included in this scope of work include wetland dredge and fill permits,
NPDES/FDEP Notice of Intent and SWPPP, FDOT utility accommodation permits,
Asbestos Handling/Disposal notification permits, Archeological/Historical preservation
permits, endangered species permits, tree removal permits, etc..
Task 3 - Bid Phase Services
Bid phase services to be performed by the CONSULTANT include:
1. Prepare Contract Document packages (i.e. drawings and specification) for CITY
advertisement and bidding purposes. Drawings to be half size (11 x 17 inch) format.
2. Distribute copies of the Contract Documents to the prospective bidders and maintain
records of the plan holders list and provide a copy of the list to the CITY.
o
Provide document mailing and pre-bid services, such as assistance with advertisement,
maintaining plan holder's list, answering questions from potential bidders, and issuing
Contract Document addenda to the plan holders.
Respond to questions from prospective bidders and suppliers and issue addenda as
appropriate. Issuance of up to three addenda is assumed in the budget for Bid Phase
Services.
5. Prepare agenda and conduct a pre-bid meeting with interested contractors and CITY
staff. Prepare and distribute meeting minutes.
DFB~RAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 4
TASK ORDER NO. '14 - AMENDMENT NO. 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
Review bid packages received, prepare bid summary, and recommend award.
Assist the CITY in conforming and preparing Contract Documents for execution by the
CITY selected Contractor. Assist in the review of Contract Documents and bonds before
forwarding to the CITY for execution.
Task 4 - Services During Construction
The specific SDC phase services to be provided by the CONSULTANT include the following:
1. Prepare agenda and conduct pre-construction meeting with selected Contractor and
CITY staff. Prepare and issue written minutes of meeting.
2. Review Shop Drawing and Product submittals for general conformance with the design
intent and provisions of the Contract Documents. Review of up to 24 submittals is
included in the budget for SDC phase services.
3. Attend monthly construction progress meetings and provide a written summary of the
issues discussed. Project meetings will be held by the Project Engineer, with the Resident
Observer in attendance. Prepare and distribute meeting minutes. Meetings will be held
at the site office. Nine monthly progress meetings are included in the budget for this
task.
Review monthly payment applications submitted in a format acceptable to the CITY.
Assist the CITY to reconcile the Contractor payment requests, clarifications, change
orders and responses to requests for quotations. A nine month construction period is
assumed in budgeting these tasks.
Respond in writing to Contractor's Request For Information (RFI) regarding the design
documents.
Review work progress at key steps to allow certifications to the SFWMD and PBCPHD
that work has been completed in substantial conformance with the Contract Documents.
Review to include verification that water services were properly pressure tested and
bacteriologically sampled to allow a "request for release of facilities to be placed into
service" to be filed with the PBCPHD. Assist the CITY in obtaining the appropriate
PBCPHD release for completed facilities.
In conjunction with CITY staff, make substantial completion and final inspections and
assist in the preparation of a Contractor "punch list". Review completion of identified
punch list items to assist in the determination that Final Acceptance has been reached by
the Contractor. Advise the CITY that Final Acceptance of the project has been reached in
accordance with the Contract Documents.
Task 5 - Resident Observation
The resident observation phase services to be provided by the CONSULTANT include the
following:
1. Provide an onsite construction observer. The resident observer will be onsite for a nine
month period. For budgeting purposes, the construction observer is assumed to be on
site for 40 hours each week for 32 weeks.
DFB\DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 5
TASK ORDER NO, 14 - AMENDMENT NO. 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
C. Assumptions
In addition to the work items discussed above, the following assumptions were made in
establishing the scope of this Amendment and associated fee. Changes and/or
modifications in the above work items or these assumptions are considered an Additional
Services Item under the terms of the contract. Assumptions include:
1. The scope and budget are based on a closed system with exfiltration basins and/or a
swale type system (i.e. no positive outfall).
2. The CITY will provide CH2M HILL an electronic version of "front end" contract
documents in MICROSOFT "WORD 2000" version format.
o
Surveying and legal work necessary to prepare document for and to secure easements
(temporary and permanent) required for installation of the piping and improvements is
the responsibility of the CITY.
Survey and acquisition of any easements (construction or permanent) for the new piping
and improvements will be the responsibility of the CITY.
The CONSULTANT will not be responsible for the preparation of RECORD drawings.
Signed and sealed RECORD drawings to be furnished by the CITY for submittal to
PBCPHD.
6. CONSULTANT is not required to attend any public meetings or hearings associated
with permits applied for the project.
7. Full time construction observation will be provided as an option to be selected by the
CITY. Construction observation hours are based on 32 weeks of actual construction
(Monday through Friday) at 8 hours per day, for a total of 1,280 man-hours.
8. The CITY is responsible for all permitting fees, including costs of public notification in
local newspapers.
9. The CITY will provide CONSULTANT an electronic version of CITY standard water
main and street details in AUTOCAD Version 12 format.
10. Permit applications covering the proposed construction work will be prepared and
submitted to SFWMD and PBCDOH.
11. The design does not include survey work for verification of horizontal and vertical
alignment of existing utilities within the project area. Utility location will be developed
based upon the best information available from the owning utilities and information
developed by the CITY. The design fee does not include survey work for establishing
horizontal and vertical alignment of new utilities either during design or during SDC.
12. The Contract Documents will be prepared as a single contract (i.e. the water main
replacement and storm water piping work will not be prepared as separate packages
within the same set of Contract Documents). No pre-purchase of materials and/or
equipment is presumed.
13. A single bidding effort is assumed. Re-bidding of the project is considered an
Additional Services item.
DFB\DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 6
TASK ORDER NO. 14 - AMENDMENT NO. 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
14. Costs for SDC phase geotechnical testing to verify Contractor's compliance with
Contract Documents are not included in the design fee estimate.
15. The design is to be based on the Federal, State and Local codes and standards in effect at
the beginning of the project. Revisions required for compliance with any subsequent
changes to those regulations is considered an Additional Services item.
D. Contract Reference
This Task Order shall be performed under the terms and conditions described within the
Agreement for General Engineering Consulting Services dated October 4, 2000 between the
City of Boynton Beach and CH2M HILL.
E. Additional Services
The following are examples of some specific Additional Services Items that may be required,
but are not included within this Amendment. Generally, a condition contrary to the work
description in Section B or assumptions of Section C (upon which the design fee is based) is
considered an Additional Services Item. Examples include:
1. Additional supervision or construction observation in excess of that specified in this
Amendment.
o
Additional permitting assistance in excess of that identified in this Amendment.
Construction phase services are based on an estimated nine month construction period
from the time of the contractor mobilization to final inspection. If the period of
construction is extended, additional time and expenses may be necessary.
Assisting the CITY in the settlement of construction contract claims.
Replacement of small diameter water mains and stormwater improvements at other
locations than those identified in this Amendment and in Task Order 14. Additional
lump sum fees will be developed as requested by the CITY for future work to include
additional drawings, revised "front ends" and the preparation of additional bid
documents. Bid services and SDC will be extended as appropriate.
Field verification (horizontal or vertical) of existing utilities identified as being within
the immediate area of the proposed mains.
Additional regulatory agency responses beyond the second response to an agency
incompleteness and/or additional information request.
Development of property descriptions of easements, road right-of-ways, etc.
Preparation of right-of-way or easement boundary surveys.
9. Threatened or endangered species and species of special concern permitting or
relocation work.
10. Archeological/Historical preservation permits, studies, or reports.
11. Surveying, flagging, or other work necessary to secure tree removal permits from the
City, County, or other jurisdictions.
DFB~DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 7
TASK ORDER NO. 14 - AMENDMENT NO. 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
12. Design modifications to the Contract Documents (i.e., change orders) required during
construction.
These and other services can be provided, if desired by the CITY, under separate Task
Order(s) or by an amendment to this Task Order. Services performed will be on an as-
directed basis in accordance with a written Notice to Proceed from the CITY.
F. Obligations of the CITY
1. The CITY shall provide the CONSULTANT in a timely manner, record data and
information related to the sewer system, water distribution system and streets within the
project as necessary for the performance of services specified herein.
2. The CITY shall review all drawings and other documents presented by CONSULTANT;
obtain advice of an attorney, insurance counselor, and others as CITY deems
appropriate for such review and render decisions pertaining thereto within reasonable
time so as not to delay the services of CONSULTANT.
3. With assistance by CONSULTANT, as described herein, the CITY, as applicant shall
obtain approvals and permits from all governmental authorities having jurisdiction over
the project. The CITY is responsible for the payment of all permit application fees.
G. Compensation
Compensation by the CITY to the CONSULTANT for all tasks except Task 4, 5, and
responses to additional requests for additional information from SFWMD and PBCDOH
will be on a lump sum basis in accordance with the above mentioned Agreement. Task 4, 5,
and responses to additional requests for additional information from SFWMD and
PBCDOH will be invoiced on a time and materials basis for the amount of work actually
required by the project. The estimated compensation for the services described in this Task
Order is $246,579 as shown in Table 1 below.
DFB~)RAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 8
TASK ORDER NO. 14 - AMENDMENT NO. 1 COMPLETION OF WATER AND STORMWATER DESIGN AND SERVICES DURING CONSTRUCTION
TABLE 1: LABOR AND EXPENSE SUMMARY
Phase I - NE 17th Ave, Stormwater Improvements
City of Boynton Beach
Labor Total
Labor Hours Cost Expenses Cost
Task 1 - Design Phase 562 $46,774 $4,386 $51,160
Task 2 - Permitting Phase 120 $11,584 $1,682 $13,266
Responses for additional 136 $12,752 $1,558 $14,310
information from SFWMD and
PBCDOH
Task 3 - Bid Phase Services 44 $3,884 $1,343 $5,227
Task 4 - Services During 770 $67,604 $5,212 $72,816
Construction
Task 5 - Resident Observation 1280 $89,800 $89,800
Totals $142,598 $103,981 $246,579
H. Schedule
The CONSULTANT will commence design and permitting services upon receipt of written
authorization and will complete all work associated with Task 1 and Task 2 of this
Amendment to Task Order 14 within six (6) months from the receipt of authorization.
APPROVED BY:
CITY OF BOYNTON BEACH, FLORIDA
Kurt Bressner, City Manager
Dated this {~lay of Iq~:~ , 2003.
SUBMITTED BY:
CH2M HILL, INC.
Vice President, Area Manager
'3uk ~r,[ 2003.
Dated thisJqday of ,
DFB\DRAFT TASK ORDER 14 AMEND 1 04 02 03.DOC 9